top of page

132kV Switchyard Engineering Works

Client

Talison Lithium

Year

2021

Location

Greenbushes, WA

Share

  • LinkedIn
  • Instagram

Our team was engaged to perform comprehensive testing and re-commissioning on several critical components for a 132kV switchyard at Talison Lithium Mine in Western Australia.

 

Working closely with the principal contractor, Divergent Engineering completed detailed engineering works including circuit breaker SF6 gas leak investigation and repair, instrument testing repair and replacement, diesel generator auto changeover wiring and commissioning, substation UPS battery management system (BMS) repair and re-commission.

bottom of page